During the month of November, the site elevation work was completed and the building team has received bids in response to our request for the site dirt work. We are excited to see the process for ground breaking is nearing its start. However, as we enter winter, we have begun to anticipate that the actual dirt work may have to begin in the spring after the ground thaws and not this month of December. The actual start time will be determined by the availability of the company who we contract with for the work.
We continue to survey interested companies on the steel work that needs to be completed for the building frame. Mr. Charlie Fink, our project engineer, is assisting us in reviewing specifications. The building team is continuing to review the options with onsite visits to current facilities serviced by the interested companies.
We are moving forward in the process. Thank you Lord for providing us direction, and helping us to be accountable in every step along the way. Thank you for helping us to stay strong in our faith, and in our encouragement of one another, so that we may continue to make progress as a church – not to build a building, but to grow a church of faithful people. Do not let this building be a distraction, but we pray Lord, that you let it be your victory through us that we are reaffirmed that in all things by faith you can do anything. We will give you praise and worship as you enable us to serve you. Amen.